V.H. Effective Date and Compliance Schedule
The FAA proposed an effective date of 30 days and a general
compliance date of 1 year after publication of the final rule. The
FAA stated in Notice 95-5 that a final rule, if adopted, would be
published by December 31, 1995, and that within 1 year of that date,
that is, by December 31, 1996, all affected certificate holders that
have air carrier certification or operating certificates issued under
part 135 at the time of publication would have completed the approval
process and obtained new operations specifications giving them
authority to conduct domestic or flag operations under part 121.
Under the proposal, persons who do not already have air carrier
certificates or operating certificates who submit applications for or
obtain air carrier certificates or operating certificates after 30
days after the publication date of the final rule would be required to
obtain part 121 operations specifications; however, these new entrants
would meet the same requirements as the affected commuters, i.e.,
delayed dates for retrofit of airplanes with certain types of
equipment.
Proposed § 121.2(c) and § 135.2(c) allow for regular or
accelerated compliance with part 121 requirements. Proposed §§
121.2(g) and 135.2(g) also require an affected certificate holder to
submit to the FAA a transition plan for moving from part 135 to part
121.
Comments: Eleven comments were received on this issue. Several
commenters express a desire for an "incremental" or "phased"
compliance schedule. Two commenters are concerned that the proposed
"turnkey" recertification event is high risk with no early rewards or
benefits.
RAA suggests revising proposed §§ 121.2(c) and 135.2(c) to
require compliance "not later than" 1 year after final rule
publication rather than the proposed "as of," and adding the word
"complete" before "14 CFR part 121 operations specifications." RAA
also suggests adding a new paragraph to the section that would state
that a certificate holder may be authorized under its transition plan
to comply with portions of part 121 instead of the equivalent portions
of part 135 in advance of being issued complete 14 CFR part 121
operations specifications. Accordingly RAA recommends adding to the
transition plan requirements of paragraph (g) a new subparagraph to
include in the transition plans provisions for interim compliance with
portions of part 121 in advance of obtaining complete 14 CFR 121
operations specifications. Other commenters also request provisions
for complying with portions of part 121 in advance of obtaining part
121 operations specifications.
Other commenters also state concerns about FAA's capacity to
facilitate the transition process on schedule. Two commenters
perceive a shortage of trained inspectors and suggest that the
compliance date be extended if an adequate number of inspectors are
not provided by mid year 1996. GAMA suggests a reevaluation of the
implementation schedule of § 121.2(d)(1), citing a questionable number
of aircraft certification service personnel to support the extensive
design approval activity certain to occur. Another commenter
expresses concern over the necessary type certification activity
surrounding modifications and suggests that 1 year is an unrealistic
compliance deadline given the current FAA Aircraft Certification
Office backlog.
RAA is concerned that the population of FAA inspectors qualified
to perform their duties under part 121 will not be able to respond to
the new part 121 air carriers. According to RAA, FAA inspectors must
be trained and qualified to help affected commuters achieve the
transition. RAA recommends a "fill in the blanks manual" to achieve
standardization among FAA regions and districts. If there is an
insufficient number of qualified FAA inspectors, the 1996 compliance
date should be delayed.
ASA proposes a standardized transition program including three
elements: (1) a fill-in-the-blanks manual for transitioning carriers;
(2) an automatic exemption and incremental approval process; and (3)
time schedules from transitioning carriers submitted to FAA.
Mesa Airlines recommends pre-formal certification meetings with
principal operations inspectors (POI's) at an early date to
familiarize both parties with the certification process outlined in
FAA Order 8400.10. According to Mesa, compliance statement
development, individual operator transition plans, GOM (general
operating manual) development, and formal certificate application
should be scheduled for the spring of 1996 to allow adequate review by
respective POI's. According to Mesa this would allow certificate
holders to be running their commuter operations under part 121 rules
by the summer of 1996. This in turn would allow for a start-up phase
for part 121 dispatch operations and modifications to the requirements
for proving runs as proposed in § 121.163 and would eliminate the
necessity for formal initial operating experience (IOE).
There were several comments on specific compliance dates. ALPA is
generally pleased with the compliance schedule, but states that the 4-
year compliance date for the installation of pitot heat indication
systems could be shortened to 2 years, given the relative ease of the
modification. Fairchild Aircraft finds fault with the fact that a 2-
year delay is provided for compliance with emergency exit handle
illumination, but no delay is allowed for compliance with §
121.310(b)(2)(ii), which would require the replacement of exit signs
on new commuter category airplanes. Mesa Airlines suggests that
compliance with part 121 crew flight and duty limitations be changed
to January 1, 1997.
FAA Response: The final rule has a 30-day effective date and a
general compliance date of 15 months after publication of the final
rule. The FAA is extending the general compliance date to be
consistent with the compliance date in the training rulemaking
referenced in Section III. E, Related FAA Action. Also, the proposed
delayed compliance dates for certain retrofit requirements have been
modified in response to comments. The final rule also establishes
delayed compliance dates for meeting the performance operating
limitations of part 121 for certain airplanes. Compliance dates are
provided in § 121.2. This section has been reorganized to separate
compliance dates for 10-19 seat airplanes and those for 20-30 seat
airplanes. Retrofit and performance requirements compliance dates are
listed on Table 1 and discussed in the appropriate place in the
preamble.
Because of the scope and significance of this rulemaking, the FAA
has already begun planning for the implementation of the final rule.
Training has been provided for inspectors who will be responsible for
overseeing the transition of the affected commuters from part 135 to
part 121 operations. Additional training planned for January 1996
will focus on the recertification and transition process. Extensive
guidance material is being prepared to assist the inspectors during
the transition process. Portions of this material will also be made
available to the affected commuters.
The FAA agrees with Mesa Airlines that meetings between POI's and
affected commuters would help facilitate the preparation of the
transition plan, which is due 90 days from today, and the planning
necessary to ensure that normal operations can continue during the
transition phase. The FAA believes that the training given to its
inspectors, the guidance material being prepared, and a cooperative
working relationship between the affected commuters and the FAA will
ensure a smooth transition to part 121 operations.
The transition plan must include the certificate holder's
proposed calendar of events that shows how and when it plans to make
changes in its operations to meet the requirements of part 121. The
transition plan should also show detailed plans for accomplishing
activities and necessary retrofits for requirements with delayed
compliance dates. The POI and the certificate holder will schedule
the inspections necessary to show compliance with part 121
requirements. When the inspections are complete and the FAA has
determined that the certificate holder can comply with part 121, the
FAA will issue new operations specifications. Until the new
operations specifications are issued, the existing operations
specifications remain in effect. In any case the existing operations
specifications expire on: (1) The date the new operations
specifications are issued; or (2) 15 months from this date of
publication, whichever is earlier. Affected certificate holders who
want to comply with certain part 121 requirements in advance of being
issued complete 14 CFR part 121 operations specifications could
include in their transition plan a phased schedule including advance
compliance for certain part 121 requirements, subject to their POI's
approval.
Table 1 - Summary of Modifications shows the compliance dates for
certain retrofit and performance requirements for affected commuters.
Many of these are required by the end of the basic 15-month
compliance period. Affected commuters should be aware that by the
specified date they must comply with all part 121 requirements, not
just the ones listed on Table 1. Although the table includes
additional items that were not listed in the table in Notice 95-5, no
new requirements are involved. Not all requirements are in the table.
The purpose of the table is to show the compliance dates for certain
equipment and performance requirements that necessitate advance
planning for purchasing and installation. Many of the delayed
requirements apply to airplanes in the current fleet, while others
apply only to newly manufactured airplanes.
It should also be noted that § 121.2(h) requires a certificate
holder to comply with corresponding part 135 requirements, as
applicable, in the interval between the effective date of this rule
and when the certificate holder is in compliance with the part 121
requirements. In addition, the intent of § 121.2(h) is also included
in specific sections that have delayed compliance dates.
This table does not apply to certificate holders currently
operating under part 121. The passenger seating configuration numbers
provided in the chart do not mean that the requirement applies only to
that size airplane but rather that the requirement is new for that
size airplane.